Perras Project Timeline Update

Project crews are currently finalizing installation of the slurry wall and beginning preparation for the new concrete work and associated earthwork for construction of the dam. The footings for the wing walls of the dam will tie into the slurry wall at both ends. The forms for the concrete dam will be built on top of the slurry wall. Finishing the concrete phase of the dam and removal of the coffer dam is targeted to be complete by mid-December 2019, with some landscaping work to be done in the spring of 2020.